SKILLFIX CONSTRUCTION – REDDITCH
2526m2
Richard from Skillfix reached out to us regarding a renovation project in Redditch.
With a pressing deadline to meet, we provided him with a quotation on May 28th, and by June 10th, our team was on-site.
Our task involved applying a High Build (HB) coating system.
During our site survey, we noticed moisture present in the slab, prompting us to suggest the use of a DMP primer alongside the High Build system.
Ultimately, we wrapped up the project in just 10 days.